The schedule for Red Brick Solar follows:
Milestone Description |
Date |
Lunenburg County Conditional Use Permit approval |
June 2022 |
VA Department of Environmental Quality approved the Permit by Rule |
March 2023 |
Final execution of PJM Interconnection Agreements |
April 2023 |
Execution of Engineering, Procurement, and Construction (EPC) Contract |
October 2023 |
Stormwater Permit Expected Approval |
Q3 2024 |
Lunenburg County Building Permit |
Q3 2024 |
Start of Construction/Notice to Proceed (NTP) |
Q4 2024 |
Commercial Operational Delivery (COD) |
Q4 2025 |