The schedule for Red Brick Solar follows:

 

Milestone Description

Date

Lunenburg County Conditional Use Permit approval

June 2022

VA Department of Environmental Quality approved the Permit by Rule                 

March 2023

Final execution of PJM Interconnection Agreements

April 2023

Execution of Engineering, Procurement, and Construction (EPC) Contract

October 2023

Stormwater Permit Expected Approval                                                                    

Q3 2024

Lunenburg County Building Permit                                                                          

Q3 2024

Start of Construction/Notice to Proceed (NTP)

Q4 2024

Commercial Operational Delivery (COD)